L'AUBA one more step

L'AUBA one more step

Since the basement was finished in the first fortnight of November, on Wednesday 18 the first wall of the future building was placed.

 


Besides, as the ground floors of the 4 duplexes have already been compartmentalized, the assembly of the two two-bedroom dwellings located on the ground floor started the following week....

… in order to have the slab of the first floor in place and protected by November 27.