L'AUBA step by step

L'AUBA step by step

In late August, after a delayed start due to administrative reasons, the excavation began and thanks to the favorable terrain it is progressing well.

 

The intense rains of September did not delay the phase of formation af bracing, footings and foundations.

 

Therefore, by the end of October a part of the basement was already covered.